Academic Center and Library Schedule

Building Project Schedule

Phase or Task Start Finish
Academic Center & Library 11/29/06 12/16/13
Programming 11/29/06 12/04/07
Prepare RFQ for Program Architect 11/29/06 03/13/07
Meet with Dr. Durgin 03/07/07 03/07/07
Send out RFQ 03/14/07 04/10/07
Question Period 03/14/07 03/27/07
Select Program Architect 04/11/07 04/24/07
Contract negotiation 04/25/07 06/12/07
Programming Sessions/Preparation 06/13/07 11/13/07
Submit COBCP Placeholder 11/02/07 11/02/07
Finalize COBCP and Program 11/05/07 12/04/07
Design (PW Phase) 07/01/09 07/01/10
Construction (C Phase) 07/02/10 10/21/13
Occupancy 10/22/13 12/16/13