Academic Center and Library Schedule
Building Project Schedule
| Phase or Task | Start | Finish |
|---|---|---|
| Academic Center & Library | 11/29/06 | 12/16/13 |
| Programming | 11/29/06 | 12/04/07 |
| Prepare RFQ for Program Architect | 11/29/06 | 03/13/07 |
| Meet with Dr. Durgin | 03/07/07 | 03/07/07 |
| Send out RFQ | 03/14/07 | 04/10/07 |
| Question Period | 03/14/07 | 03/27/07 |
| Select Program Architect | 04/11/07 | 04/24/07 |
| Contract negotiation | 04/25/07 | 06/12/07 |
| Programming Sessions/Preparation | 06/13/07 | 11/13/07 |
| Submit COBCP Placeholder | 11/02/07 | 11/02/07 |
| Finalize COBCP and Program | 11/05/07 | 12/04/07 |
| Design (PW Phase) | 07/01/09 | 07/01/10 |
| Construction (C Phase) | 07/02/10 | 10/21/13 |
| Occupancy | 10/22/13 | 12/16/13 |